ConcernedAndrew WeissSep 8, 2026

The Longview co-op president said a $6.5 million capital project is two years behind because the building department can't keep up with reviews and inspections, with $19.5 million in projects at stake.

Board of Trustees - Sep 8, 2026 · 1:37:29 →
ConcernedChris SabatoSep 8, 2026

The co-op board member and former Port Chester police officer detailed how fire standpipe work passed fire department inspection weeks ago but still sits unreviewed by the building department.